UPDATE (May 18, 2021): There will be no planned outage today (as previously planned) due to rain. ATCO will resume work on Wednesday, May 19, 2021. There will be 2 planned outages on Tuesday, May 25 and Wednesday, May 26, 2021.
ATCO will be be working on the power line between the Landry Heights turn off to the old Grovedale store to make this portion of line more reliable. Work will commence May 10 and hopefully be wrapped up by May 21.
ATCO will have traffic control for a large portion of the project as it progresses. There will be 1 large outage that includes all of Landry Heights to North of the old store on May 13 for approximately 5 or 6 hours. After that there will be smaller localized outages working from Grovedale North to Landry Heights. ATCO will not be working on the weekends.