Highway 666 Update from Alberta Transportation – June 21, 2024

Contractors are making progress on Highway 666, focusing on the 1.4 km section slated for gravel conversion. To address drainage concerns, four new centerline culverts will be been installed.

Milling and paving of the remaining 6.3 km of Highway 666 are scheduled to begin in July, pending weather conditions.

For more information, please visit www.511alberta.ca