Greenview would like to take this opportunity to provide the residents of both Grovedale and Landry Heights with a brief update on the current water/wastewater projects within the Hamlets. Information regarding connection fee(s) can also be found below.

Water Treatment Plant

Construction of the Grovedale Water Treatment Plant (WTP) is anticipated to be complete in late 2020. Water production is expected for December 15, 2020 pending successful commissioning of the WTP.

Grovedale

Construction of the Grovedale water system and sewer system alterations is anticipated to be complete by October 15th, 2020 with a chance of early completion . Residents will be allowed to connect their service lines once the contractor achieves total completion and the line is commissioned. A notice will be issued once this milestone is achieved.

Total completion of the Grovedale water system and WTP will be required before water is available. This requirement will not affect service installation timelines but may impact water delivery if there are construction delays .

Landry Heights

Construction of the Landry Heights water system is anticipated to be complete by August 31, 2020 with a chance of early completion . Residents will be allowed to connect their service lines once the contractor achieves total completion and the line is commissioned. A notice will be issued once this milestone is achieved.

Total completion of the Grovedale water system and WTP will be required before water is available. This requirement will not affect service installation timelines but may impact water delivery if there are construction delays .

Connection Fees

Prior to connecting, residents will need to contact Corporate Services to facilitate the connection fee payment or financing options for the connection fee ($12 ,500.00 for water and $12,500.00 for new sewer connections where applicable). Corporate Services will arrange a date for each resident to meet staff in the Grovedale area to conveniently arrange sign up and financing. Residents can contact Corporate Services at 780-524- 7632 or 780-524-7642 to sign up.

Residents are required to make arrangements for the connection fee prior to connecting to  our system as per policy.

Note: The connection fees do not cover the cost of the installation of your water and/or sewer lines. Residents are to arrange and pay separately for the service installation on their property.

Important Note

Again, there will be no water to your home until the Grovedale Water Treatment Plant and associated water lines are successfully commissioned, regardless of whether or not your home has been connected to the water system.

 If you have any questions or concerns please contact me at 780-524-7638.